Weekly Brief – 10/3/25
Downtown
- Still awaiting blacktop contractor.
- Work in the 1100 block is at a standstill pending arrival of the trench drain.
- Meeting with ComEd on Monday regarding electric meters; hoping to move that portion of the project forward.
- Survey work in the 1200 block will begin Monday to keep crews moving.
- Estimated shipping date for street lighting is now November 21 (moved up from the original December timeline).